






|
By Mark Langdon, published in Zig Zag
Railway's Magazine, Switchback, Issue 117, Sept 2005
With the build up of military forces in Australia following the
entry of Japan into the Second World War, there was a corresponding
increase in demand for petrol, which was the lifeblood of modern
armies. To meet this demand it had been determined in April 1942
that storage facilities for an extra 46,000,000 gallons of motor
spirit would be required by the end of October 1942.1 To hold this
fuel new storage facilities would need to be constructed that would
fit in with the operational plans of the army and eight sites were
selected around Australia at Townsville, Gladstone, Brisbane,
Melbourne, Adelaide, Port Pirie and Albury, but only one, at Newnes
Junction, would not be located at a coastal port. Priority would be
given to the facilities in Queensland and Western Australia, with
the tanks in Townsville the first to be built.2
Although the exact reason for selecting Newnes Junction is
uncertain it appears that it stems from a request from the army in
March 1942 to use the National Oil Company's storage tanks at both
Glen Davis and Newnes Junction to store petrol then held in Sydney.
The government expected Japanese raids on the Sydney storage depots
and wished to 'difuse' this petrol about the country. National Oil
had the capacity to store three million gallons of petrol,3 the
capacity proposed for the new storage facility at Newnes
Junction.
In order to make use of their expertise, final site selection,
construction and operation of the new storage facilities would be
delegated to the major oil companies operating in Australia.4
However, construction of the new tanks was delayed owing to a
shortage of suitable steel and ultimately a standard design of tank
that made best use of the available resources evolved. Each tank
would have capacity of one million gallons,5 with a concrete outer
shell and a steel liner, with the steel plate coming from refugee
cargoes,6 cargoes that had originally been bound for areas now
occupied by the Japanese.
Responsibility for site selection at Newnes Junction was jointly
delegated to the Commonwealth Oil Refineries and the Vacuum Oil
Company7 and their construction engineers were at Newnes Junction
early in May 1942.8 However, in the following month, the work was
re-allocated amongst the oil companies and the Commonwealth Oil
Refineries became solely responsible for the Newnes Junction site.9
Three, one million gallon capacity tanks were to be erected at
Newnes Junction, with the sides of each tank lined with half inch
mild steel plate and eight inches of reinforced concrete, while the
tank bottoms were unlined reinforced concrete with a water seal. A
concrete pump house was located adjacent to the tanks, while a
twelve thousand gallon capacity gravity feed tank and a subsidiary
pump house were to be built next to the up sidings at Newnes
Junction Railway Station. To enable the transfer of petrol to rail
tank cars,10 six filling points were located next to National Oil's
loading facility.11 Also on site was a concrete office building and
a foam generator house.12
In 1942 the Department of the Army requested the New South Wales
Railways to recondition the first fifty-one chains (1000m) of the
Wolgan Valley Railway,13 most likely so that materials for the new
tanks could be delivered along this section of line direct to the
work site. In May 1943 construction of a vehicle filling point that
would enable four road tankers to be filled simultaneously was also
commenced on the Chifley Road below Newnes Junction.14 However, the
three tanks and associated facilities were not ready until December
1943,15 having cost over £86,000 to build.16 The National Oil
company was then asked if they would safeguard the tanks until they
were brought into use,17 but it appears that the facility was never
used as the twelve thousand gallon gravity tank was not
installed,18 nor, apparently, was the vehicle filling point
completed.19 Finally, in September 1944, it was proposed that a
portion of the fuel depot be dismantled and used elsewhere.20
This proposal was apparently not proceeded with and it was not
until December 1946 that the Joint Planning Committee of the
Department of Defence discussed the future use of all the bulk
storage depots that had been built during the war. It considered
that only the tanks at Alice Springs, Tocumwal and Wallangarra be
retained and the remainder be disposed of as there was no strategic
reason for their retention21 (these three facilities had been built
earlier in the war using a number of standard twelve thousand
gallon steel tanks22).
In November 1947 the complete facility was offered to National
Oil,23 however their existing facilities were sufficient to meet
their requirements and they declined the offer.24 The Commonwealth
Government then circularised all the major oil companies,25 with
the offer of the Commonwealth Oil Refineries being accepted to
purchase all of the removable assets, including the twelve thousand
gallon steel tank, all the pipelines and associated fittings and
the 'Simplex' Airfoam plant for a price of £1,550.26 With the
main storage tanks remaining unsold the commonwealth government
then purchased, in 1950, five acres of land surrounding them to
avoid the cost of their demolition27 (an area of over twelve acres
had originally been leased for the depot). Efforts were again made
to sell the site in 1965,28 but it apparently remained the property
of the commonwealth government until it was eventually sold to
Clarence Colliery. |